Hiring a plasterer, explained
What the trade does, how each job works, what a quote ought to contain, and what to ask before the work starts.

Does Artex contain asbestos? What to check before sanding
Textured coatings put up before 2000 may contain asbestos, and sanding one is the thing not to do. What to test, the three routes, and why overboarding is the usual answer.
How to choose a plasterer, and what to ask
Plastering is unregulated and there is no register to look anybody up on. That changes what is worth asking, and makes four questions do most of the work.
Skim or replaster: which one your wall needs
A skim is a finish coat over something sound. Replastering means floating a bare wall first, and it is roughly twice the work. Tapping the wall tells you which you have.
How long does plaster take to dry? When you can paint
Fresh plaster goes from pink to pale as it dries, and the timing depends on the coat and the room rather than on a rule. Painting too early traps moisture and the paint comes back off.
Lime or gypsum plaster: why it matters on an old wall
A solid wall built before about 1919 has to breathe. Gypsum on one traps moisture in the masonry, and putting that right means hacking the gypsum off and starting again.
Cracks in plaster: why they appear and which ones matter
Hairline cracking in a new skim is shrinkage and is cosmetic. A crack that follows a line, widens at one end or reopens after filling is telling you about the structure behind it.
Which render to use, and do you need permission
Sand and cement, monocouche and silicone thin-coat behave differently, cost differently and last differently. And rendering a house is not always permitted development.
Replastering after damp: what has to happen, in order
Plastering over a damp wall hides it for a winter. The order is find the cause, fix the cause, let it dry, then replaster, and the last step is the shortest of the four.
Preparing a room for a plasterer
What to move, what to take off the walls, and what the plasterer expects to find. Half a day of preparation is the difference between a one day job and two.
Dry lining finishes: tape and joint levels 1 to 5
Taped and jointed board is specified by finish level, and the number decides how much filling and sanding is in the price. Most domestic work wants level 4 and gets quoted as though it were level 2.
Can you plaster over paint, tiles, wallpaper or Artex?
Yes over sound paint, once it is cleaned, keyed and primed with a bonding coat. Wallpaper comes off first, tiles nearly always do, and a textured ceiling from before 2000 gets tested before anyone scrapes it.
Mist coat on new plaster: the ratio, the paint, the method
A mist coat is cheap matt emulsion thinned with water, commonly around three parts paint to one part water, rolled onto plaster that has dried right through. It soaks in, seals the surface and gives the topcoats something to grip.
Is my wall load bearing? The checks, and who confirms it
What sits above the wall, which way the joists run and what it is built from all point to the answer, but only a structural engineer can confirm it. Removing a load bearing wall needs building control approval.
Plasterboard types: which board goes where, and how thick
Standard board for dry rooms, moisture-resistant board for kitchens and bathrooms, fire-rated board where a fire rating is specified. On a ceiling, 9.5mm board suits joists up to 400mm apart; wider spacing needs thicker board.
Plasterboard patch repair: how to fix holes of any size
Screw holes take filler. Holes up to a few centimetres take a mesh patch, a fist-sized hole needs a backing piece behind it, and anything bigger gets a new piece of board cut back to the studs. Check for cables before you cut.
Painting pebbledash, or removing it: how to decide
Sound pebbledash can be painted with masonry paint once cracks and hollow patches are repaired. Removing it often damages the brick behind, so a test patch comes before any decision to strip a whole wall.
How to find the studs in a wall, and fixings that will hold
Studs usually sit 400mm or 600mm apart, and a stud detector or a magnet on the screw heads finds them. Heavy things go into a stud or a nogging; cavity fixings in the board are for lighter loads.
Screed drying time: walking on it, tiling and flooring
Light foot traffic after a day or two on a flowing screed and a few days on sand and cement. Before tiling or flooring, allow about a day per millimetre for the first 40mm and slower beyond, then confirm with a moisture test.